Mast Crane Deck Work Mar 16 and 17
Due to the fabulous work completed on Wednesday and Thursday, March 16 & 17, the new mast crane dock is 98% complete (see following photos). The major contributors to this
Due to the fabulous work completed on Wednesday and Thursday, March 16 & 17, the new mast crane dock is 98% complete (see following photos). The major contributors to this
Hooray! Spring is coming and the snow is starting to melt. This has allowed us to resume work on the mast crane deck replacement project. Project leader Al Hallworth organized
Last fall (2021) the mast crane deck and wall replacement project was started. Under the direction of Al H, many club members turned up to help remove the old decking
In preparation for the coming season and hopefully greater use of the clubhouse facilities, the two bookshelf units donated by Herb H. have been repaired and repainted. Many thanks to
Hello Fellow Sailors! Thanks to Al Duffin and Harry Hallworth for doing the investigative work and acquiring quotes, this work was deferred as there was a substantial cost. I asked